Bid Classification: |
Construction
|
||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Bid Type: | RFQ | ||||||||||||||||
Bid Number: | R22-31 | ||||||||||||||||
Bid Name: | Squamish Public Work Salt Shed Relocation & Early works | ||||||||||||||||
Bid Status: | Closed | ||||||||||||||||
Published Date: | Wed Apr 20, 2022 5:13 PM (PDT) | ||||||||||||||||
Bid Closing Date: | Wed May 18, 2022 3:00 PM (PDT) | ||||||||||||||||
Time-frame for delivery or the duration of the contract: | Refer to project document | ||||||||||||||||
Negotiation Type: | Refer to project document | ||||||||||||||||
Condition for Participation: | Refer to project document | ||||||||||||||||
Electronic Auctions: | Not Applicable | ||||||||||||||||
Language for Bid Submissions: | English unless specified in the bid document | ||||||||||||||||
Submission Type: | Hard Copy Submissions Only | ||||||||||||||||
Submission Address: | Kinetic | ||||||||||||||||
Public Opening: | No | ||||||||||||||||
Description: |
INVITATION TO QUOTE You are invited to submit a quotation for the following:
If you are not bidding this project, please let us know and we will stop sending you tender information.
Inquiries Direct all inquiries to Jason Festing via email tenders@kineticconstruction.com
Submitting your Quotation Submit quotations via email tenders@kineticconstruction.com We request that you submit your quote two hours prior to the tender closing, as we require time to compile the general tender. Quotations must remain valid for a period of thirty (30) days after the general tender close.
Personal emails are not monitored on a regular basis on tender day: use the above email to ensure your quote is received. Kinetic reserves the right to accept or reject any quotation and to request references for any bidder.
Refer to the Supplemental Specifications and Scope of Work for additional requirements and clarifications. The Supplemental Specifications and Scope of Work are to be read into and form a part of the Drawings and Specifications and Tender Documents for the project and the whole shall constitute part of the Contract Documents.
All requirements indicated on the drawings, specifications and addenda are to be included as part of the Work; however, the General and Supplementary Conditions and Scope of Work may include additional requirements over and above those of the drawings and specifications. Review all sections of the specifications to determine the requirement for submittals such as shop drawings, samples, mockups and engineered drawings. All requirements contained within the tender documents are to be included in the bid. No claims for extras will be accepted unless exclusions are clearly and specifically identified in the Contractor’s bid. The Bidder is to report any discrepancies prior to submitting the bid.
We sincerely appreciate the time you will spend on this estimate. |
||||||||||||||||
Bid Document Access: | Bid Opportunity notices and awards and a free preview of the bid documents is available on this site free of charge without registration. Please note, some documents may be secured and you will be required to register for the bid to download and view the documents. There is no cost to obtain an unsecured version of the document and /or to participate in this solicitation. | ||||||||||||||||